San Buenaventura Supercritical Power Project

San Buenaventura Supercritical Power Project

       

San Buenaventura is a 500MW coal-fired supercritical power project under construction in the Quezon province of the Philippines. Scheduled for commissioning in 2019, it will be the first supercritical power plant in the country.

San Buenaventura Power (SBPL) is the owner and operator of the supercritical power facility.

Meralco PowerGen Corporation (MGen), a subsidiary of Manila Electric Company (Meralco), holds the majority share of 51% in SBPL, while the remaining is owned by New Growth, a subsidiary of Electricity Generating Public Company (EGCO Group).

SBPL started construction on the project in December 2015, after securing PHP42bn ($896m) funding from a consortium of Philippine banks in November 2015, which represented the country’s biggest exclusive Peso project finance facility.

San Buenaventura power plant details

The San Buenaventura coal-fired power plant is being constructed in the premises of an existing plant in the Mauban municipality of the Quezon region, approximately 130km south-east of Manila.

Using state-of-the-art supercritical boiler technology, the San Buenaventura plant will operate at higher pressures leading to significantly more efficient and less-emitting power generation, compared to conventional coal-based power plants.

The San Buenaventura power plant will use sub-bituminous coal as fuel, which will be transported from the on-site coal yard to the boiler by covered overland conveyors.

The supercritical coal power plant will also be fitted with an electrostatic precipitator for fly ash capture and removal and a seawater-based flue gas desulfurisation (FGD) system to reduce emissions.

It will feature a covered turbine deck to protect the personnel from adverse climates as well as to facilitate easy plant maintenance.

Power off-take

The gross installed capacity of the San Buenaventura power plant will be 500MW. A total of 455MW of power will be sold to the country’s largest electricity distributor Manila Electric Company (Meralco), under a 20-year power purchase agreement (PPA).

The PPA was approved by Philippines’ Energy Regulatory Commission in 2015.

San Buenaventura power project construction timeline

The boiler installation for the plant was completed during the last quarter of 2017. SBPL initially planned the plant start-up and grid connection in the fourth quarter of 2018, but rescheduled it for June 2019.

Financing

A consortium of banks led by BDO Unibank extended PHP42.15bn ($896.3m) of loan facility for the San Buenaventura supercritical power plant in November 2015.

Metropolitan Bank and Trust (Metrobank), China Banking Corporation, Rizal Commercial Banking Corporation, and Philippine National Bank (PNB) form the consortium. Each member of the consortium provided PHP8.42bn ($178.79m).

BDO Unibank was the loan facility agent, while Metrobank was the collateral trustee. The banks also act as joint bookrunners and joint issue co-ordinators.

Latham and Watkins acted as financial advisor for the financing deal, which has a loan period of 15 years.

Contractors involved

The engineering, procurement, and construction (EPC) contract for the project was jointly awarded to Daelim Industrial and Mitsubishi Corporation in December 2015.

Daelim Industrial is the main construction contractor responsible for civil works as well as the construction and installation of associated infrastructure.

Mitsubishi Corporation designed and supplied industrial boilers, steam generators, and turbines for the San Buenaventura supercritical power project.
Related News
  • Additive Storage

    Additive Storage

    March 13, 2018Additives are chemicals and materials blended into base cement slurries to alter the performance of the cement. Due to the inherent nature of base cements (Neat, Portland and Pozzolanic) and because o...view
  • Bulk Storage Dome

    Bulk Storage Dome

    October 22, 2018Dome Structural system provides a unique solution to the bulk storage industry. Remained committed towards sustainability and improving the local economies, the coal dome manufactured LF Group are ...view
  • Why choose the 3D Space Frame Structures?

    Why choose the 3D Space Frame Structures?

    April 21, 2018Structural efficiency, rigidity, reduced deflections, integration of services, resilience, ease & speed of manufacturing and installation are some of the biggest advantage of 3D Space Frame Struct...view
  • The first CIMC modular housing in the United States opened

    The first CIMC modular housing in the United States opened

    November 16, 2018Recently, the graduate dormitory of the University of California, Berkeley, which was designed and built by CIMC Modular Construction Investment Co., Ltd. (hereinafter referred to as “CIMC Modular”)...view
  • Spatial Structure1

    Spatial Structure1

    November 23, 2017Many applications require roofs or covers that are flat, or nearly flat. Spatial structure provide efficient solutions for these requirements. The most common Spatial Structure geometries are called "...view
  • Environmentalists Sue Trump Over Coal Pollution Ahead Of State Of The Union

    Environmentalists Sue Trump Over Coal Pollution Ahead Of State Of The Union

    February 2, 2018An environmental group sued the Trump administration for delaying regulations on coal power plant pollution just ahead of the president's State of the Union address Tuesday during which Trump plans to...view
  • TEL:+86 516 8595 0258
  • FAX:+86 516 8595 0278
  • Email:marketing01@cnxzlf.com
  • ADDRESS:222, Block B, Diamond International, Guozhuang Road, Xuzhou, Jiangsu, China

[QUERYS RESOURCE ID #57]

Total quantity:868, Total process time:0.27104378 ms

[FILES LOADED]

Total quantity:22

Use Memory: 12.2MB

Time-consuming: 0.45076 ms