Two-Year, $10M Retrofit of Rogers Center Roof Completed

Two-Year, $10M Retrofit of Rogers Center Roof Completed

In the almost 28 years since the Rogers Center—then known as Sky Dome—became the home of the MLB' s Toronto Blue Jays in June, 1989, the once cutting-edge facility has become the 7th oldest of the league's 30 active stadiums. The stadium's retractable roof was considered a marvel of engineering at the time of completion, though in the years since, five other retractable roof MLB stadiums have joined the mix, and several stadiums devoted to other sports have been built as well. While talk of replacing the Rogers Center has bubbled up in recent years as multipurpose facilities fall out of favor within the league, the now-sole tenant Toronto Blue Jays' parent company Rogers have indicated they have no interest in a new facility, instead committing to upgrade the existing stadium. The most recent of these upgrades was a $10 million retrofit of the stadium's signature retractable dome roof and its associated systems, which was completed earlier this year in time for the start of the upcoming Toronto Blue Jays home opener.
Two-Year, $10M Retrofit of Rogers Center Roof Completed

The stadium's dome roof is still unique among retractable roof designs, which along with antiquated technology and out-of-production parts, created some site-specific challenges for contractor New Electric. The dome consists of three moving panels and one fixed section, has a surface area of 8 acres, a weight of 11,000 tonnes, and a maximum clearance of 282 feet over the field. When opening, two of the moving panels slide on tracks and fit under the fixed northern panel, then the third moving panel rotates to fill the void in a process that took roughly 20 minutes prior to the recent upgrades.

A crew of 30 worked for two years to carry out the much-needed roof upgrades, which include a new OT (Operations Technology) network and control system, as well as a rooftop weather station that tracks weather systems to better predict game-time conditions for roof openings and closings. The new OT network and control system comes with a reduction in the required number of staff to open or close the roof, as well as a 46% decrease in the time needed to operate the roof. Other valuable improvements include fault tolerance, self-diagnostics, and reporting capabilities not offered by the previous system, allowing for simplified troubleshooting.
Two-Year, $10M Retrofit of Rogers Center Roof Completed

With one major upgrade to the Rogers Center now complete, Blue Jays fans are looking to the future of the stadium, which is at an important crossroads in its history. Blue Jays President and CEO Mark Shapiro has indicated his intention to invest heavily in the stadium in the coming years, with talk of a full "re-envisioning" of the landmark, turning the Multipurpose stadium into a baseball specific venue.

What would you like to see happen to the Rogers Center in the coming years? Let us know in the comments section provided at the bottom of this page. You can keep track of the ongoing talks of upgrades to the Rogers Center by visiting our Forum thread. 

Related News
  • “Who Moved My Btus?”The Pitfalls of Extended Coal Storage

    “Who Moved My Btus?”The Pitfalls of Extended Coal Storage

    July 16, 2019Many coal power stations have recently been operating at historically low capacity factors or have even undergone extended economic shutdowns. This can result in coal stockpiles that are exposed to th...view
  • Longest overpass in Changsha county to be completed in August

    Longest overpass in Changsha county to be completed in August

    August 10, 2018The main bridge for the Xingsha Avenue pedestrian bridge project was installed on July 22 and is expected to be completed by the end of August, according to the key project management bureau of Changs...view
  • Was weather a factor in USA practice facility collapse?

    Was weather a factor in USA practice facility collapse?

    November 23, 2017The big question on everyone's minds: how could this happen?That's what insurance investigators are working to determine after a practice facility under construction at the University of South Alabama...view
  • Space Frame with Free Shape

    Space Frame with Free Shape

    September 17, 2018The basic forms of latticed shells are single-curvature cylinders, double-curvature spheres, and hy- perbolic paraboloids. Many interesting new shapes can be generated by intersecting and combining th...view
  • 2017 Steel Price Forecast

    2017 Steel Price Forecast

    November 20, 2017Steel building pricing is more complicated than you might assume. Steel is a global commodity, and that means the price of steel varies on a daily basis. Prices can be influenced by several factors, i...view
  • Beijing's new international airport takes shape, eyeing 2019 launch

    Beijing's new international airport takes shape, eyeing 2019 launch

    November 20, 2017Beijing's new international airport is taking shape as the steel structure of its terminal buildings was completed Friday.Authorities said the airport, currently known as Beijing Daxing International ...view
  • TEL:+86 516 8595 0258
  • FAX:+86 516 8595 0278
  • Email:marketing01@cnxzlf.com
  • ADDRESS:222, Block B, Diamond International, Guozhuang Road, Xuzhou, Jiangsu, China

[QUERYS RESOURCE ID #57]

Total quantity:801, Total process time:0.22924423 ms

[FILES LOADED]

Total quantity:22

Use Memory: 11.5MB

Time-consuming: 0.39115 ms